Green Technologies FZCO
An environmentally focused Organization

 



i Replacement of Chiller Plant –
Hyatt Regency Dubai & Galleria
   

Replacement of Chiller Plant – Hyatt Regency Dubai & Galleria

The Hyatt Regency and Galleria, commissioned the services of ServeU under the management of a LEEDTM Accredited Professional, to Engineer and Project Manage the retrofit of the 5000 Ton Chiller Plant. Green Technologies provided the services of the LEEDTM Accredited Professional, for Engineering, Energy Modeling and Project Management, from concept to completion. The project involved the replacement of the 23 year old chiller plant, without disrupting the operations of the hotel.

The retrofit included
- 5000 Tons of Centrifugal Chillers
- 6000 Tons of Cooling Towers
- Condenser water Pumps.

New equipment included
- Chiller Plant Manager
- Variable Speed Chillers
- Variable Flow Primary Pumping
- Chiller Plant Manager
  Project Highlights
- No disruption to hotel operations
- Completed on time & on budget
- Moving of 400,000 Tons of equipment in an   operating hotel.
- Fully Automated Chiller Plant with Energy   and Water Management Capabilities
i 1

Project Title:
Replacement of Chiller Plant – Hyatt Regency Dubai & Galleria

Client:
Hyatt Regency Dubai & Galleria

Engineers and Project Managers:
Green Technologies FZCO

Scope of work Includes

- Feasibility Study on   the replacement of the   5000 Ton Centrifugal   Chiller Plant.

- Refrigerant Application   and Energy Study   R500, R134, R 123.

- Energy Modeling   Chiller Power and   Water Use, based on   DOE 2.1 E Energy   Modeling Software.

- Life Cycle Analysis,   including Value   Engineering.

- Detailed Design,   Replacement   Methodology, and   Contract Documents.

- Project Management   from Concept To   Completion.

- Post contact Energy   and Water   Management.