Hyatt
Regency Dubai - (2003)
The
project involved the replacement of the 23 year
old chiller plant.
The retrofit
included
-
5000
Tons of Centrifugal Chillers
-
6000
Tons of Cooling Towers
-
Condenser
water Pumps
New
equipment included
-
Chiller
Plant Manager
-
Variable
Speed Chillers
-
Variable
Flow Primary Pumping
- Detailed
design, methodology, contract documents
-
Complete
energy modeling using DOE 2.1E
-
Life
Cycle analysis, including value engineering
Al
Wasl Hospital (1989)
Installation of new 750-ton chiller, cooling tower and auxiliary
systems to supplement the existing battery of chillers.
The scope included
design, supply, installing and commissioning of new and existing
chiller.
|
|
|
|
 |
|
Union
Tower - (2002)
Carried out feasibility study for
-
Retrofitting chillers or connecting to district cooling system.
- Work included Energy modeling and performing life cycle analysis.
- The installed capacity of the chiller plant was two of 750 T retrofitted to
two of 400 T.
Marley
Cooling Tower Study (1998)
-
Study of water-cooled and air cooled chillers gulf wide.
- The study was based on life cycle analysis of air and water cooled systems.
- The study determined the transition point for switching from air-cooled to
water-cooled chillers. In 1998 the transition from air-cooled to water-cooled
chillers was at 1000T.
|
|
|
|
|
|